The Selangor WTE project achieved significant progress
發(fā)布日期:2025-08-28
點(diǎn)擊次數(shù):56
字體顯示:

【大】

【中】

【小】

馬來西亞雪蘭莪州大型再生能源電站項(xiàng)目于近日取得里程碑式雙突破。8月22日,項(xiàng)目二期工程1#鍋爐水壓試驗(yàn)一次成功;23日,項(xiàng)目一期工程倒送電工作圓滿完成。兩大核心節(jié)點(diǎn)的順利實(shí)現(xiàn),為后續(xù)的設(shè)備調(diào)試與并網(wǎng)發(fā)電奠定了堅(jiān)實(shí)基礎(chǔ)。

The large-scale renewable energy power plant project undertaken by the company recently reached two milestone breakthroughs. On August 22, the Phase II project’s #1 boiler hydrostatic test was successfully completed in one attempt; August 23, the back-energization work for the Phase I project was also successfully completed. The smooth achievement of these two core milestones has laid a solid foundation for subsequent equipment debugging and grid connection.

本次水壓試驗(yàn)是對二期1#鍋爐制造、焊接、安裝質(zhì)量的一次“大考”。試驗(yàn)過程中,系統(tǒng)壓力穩(wěn)步提升至預(yù)設(shè)最高壓力并保持穩(wěn)定,所有承壓部件、閥門及焊口無一泄漏,管道無變形,試驗(yàn)取得圓滿成功。這標(biāo)志著二期項(xiàng)目全面轉(zhuǎn)入安裝階段。

This hydrostatic test was a "major examination" of the manufacturing, welding, and installation quality of the Phase II #1 boiler. During the test, the system pressure was steadily increased to the preset maximum pressure and maintained stably. All pressure-bearing components, valves, and welds showed no leakage, and no pipeline deformation occurred, marking the complete success of the test. This indicates that the Phase II project has fully transitioned into the installation stage.

緊隨其后的倒送電工作是項(xiàng)目由建設(shè)階段轉(zhuǎn)向調(diào)試階段的關(guān)鍵一步。此次操作成功將外部電網(wǎng)電源可靠地接入一期工程的配電系統(tǒng),意味著電站首次獲得了“外部血液”。主變壓器受電沖擊成功,各項(xiàng)參數(shù)正常,電源順利接入6.6KV配電系統(tǒng)。此后,一期項(xiàng)目廠內(nèi)的各系統(tǒng)設(shè)備將陸續(xù)獲得電源,逐步開啟單體調(diào)試和系統(tǒng)調(diào)試工作。

The subsequent backfeeding work is a critical step in the project’s transition from the construction phase to the debugging phase. This operation successfully connected the external grid power supply to the Phase I project’s distribution system reliably, meaning the power plant received "external blood" for the first time. The main transformer underwent a successful energization impact, with all parameters normal, and the power supply was smoothly connected to the 6.6KV distribution system. Thereafter, various systems and equipment within the Phase I plant will gradually receive power, and individual and system debugging work will be initiated step by step.